Since 1999 | ISO Certified

Preparation of Detailed Project Report of Sewerage System in Lonavala

Lonavala Municipal Council

Preparation of Detailed Project Report of Sewerage System in Lonavala

Name of Work- Lonavala Municipal Council: Preparation of Detailed Project Report of Sewerage System for Lonavala Municipal Council under UIDSSMT

Work completion Date- 2015

Project Cost- 29.30 Cr.

Survey- 35 Sq. Km. and 105 Km

Description of Work- Study & Analysis of General, Configuration & Strata, Climate, Population, Topographical Survey of City, Need for formulation of New scheme, Proposed scheme, Cost of the scheme, Financial pattern of the scheme, Annual burden.

  • Project Management Consultancy Services as below:
  1. Topographical Survey 35 Sq. Km. and 105 Km Road Survey.
  2. Soil Investigation of 90 Trial Pits.
  3. Preparation of Contour Drawing.
  4. Design of drainage districts.
  5. Hydraulic Design.
  6. Preparation of Cost Estimates.
  7. Preparation of Detailed Project Report.
  8. Total Length of Sewer Lines: 114 Kms.
  9. Presentations at GoM.