Name of Work- Shrivardhan Municipal Council: Preparation of Detailed Project Report of Water Supply for Shrivardhan Municipal Council under UIDSSMT
Work completion Date- 10th Aug. 2009
Project Cost- 11 Cr.
Survey- 40 Ha. area.
Description of Work- Study & Analysis of General, Configuration & Strata, Climate, Population, Topographical Survey of City, Rate of water supply & Daily water requirement, Present water supply arrangement, Need for formulation of New scheme, Proposed scheme, Cost of the scheme, Per capita cost of the scheme, Financial pattern of the scheme, Annual burden, Cost of the water per 1000 lit., Revenue Collection.
- Topographical Survey, of 40 Ha. area.
- Preparation of Contour Map.
- Topographical Survey for ESR & GSR
- L-SECTION drawing of Raw water rising main.
- L-SECTION drawing of pure water gravity mains feeding different reservoirs.
- Typical drawing of connections for proposed Service Reservoirs with varying capacities.