Name of Work- Preparation of Detailed Project Report for strengthening & widening Road to 2-Lane Road in Daund & Shirur Taluka in PMRDA Jurisdiction. (21.5 Km)
Work completion Date-25.08.2021
Project Cost- Rs. 2283 Lakhs
Survey-
- Engineering & Topographical Survey using Total Station (TS) & Differential Global Positioning System (DGPS) and Fixing of Permanent Bench Mark
Description of Work-
- Engineering & Topographical Survey using Total Station (TS) & Differential Global Positioning System (DGPS) and Fixing of Permanent Bench Mark
- Excavation & Taking Trial Pits for roadway in hard murum and boulder including dressing section to the required grade, chamber and side slope and conveying the excavated material with all lifts up to a lead of 50 m.
- Preparation of Detailed plan, sand estimate of road
- Geometrical design of road horizontal and vertical curves for design speed specified by IRC including carrying out trail for optimizing of civil coast.
- Survey of C.D. work including taking L-section of road, catchment area plan by traverse method and taking trial pits of size 1.50 m. x 1.50 m x 1.50 m
- Preparation of detail plans & estimate.
- Taking CBR tests (Field Determination Test)
- Preparation of Detailed Project Report
- Providing technical support to PMRDA in preparation of DTP.